Project Timeline
Hanbando Offshore Wind secured its Electricity Business License in March 2025, establishing a firm foundation for full-scale development. Currently, key project phases including environmental impact assessments, marine traffic safety assessments, along with geophysical and geotechnical surveys being conducted in sequence. With a focus on stable project execution and successful construction, the project targets commercial operation in the 2030s. An expected timeline (subject to technical, permitting and route to market advancements):
-
Site Screening approx. 6 months
Review of candidate offshore areas, environmental and meteorological assessment
-
Wind Resource Measurement minimum 1 year
Installation of measurement equipment, wind resource evaluation
-
Electricity Business License 1 year
Approval by the Ministry of Trade, Industry and Energy
-
Permitting, Surveys & Project Financing 5 years
Environmental Impact Assessment, Marine Traffic Safety Assessment, financial structuring
-
Construction Phase 2–3 years
Foundation installation, submarine cable laying, turbine installation, commissioning
-
Operation Phase 25–30 years
Commercial operation and long-term operations & maintenance